Union Cabinet Approves Doubling of Two Important Railway Lines Passing Through Telangana & Andhra Pradesh States





Union Cabinet Approves Doubling of Two Important Railway Lines Passing Through Telangana & Andhra Pradesh States

Shri Arun Kumar Jain, General Manager, South Central Railway informed that the Cabinet Committee on Economic Affairs chaired by Hon’ble Prime Minister, Shri Narendra Modi has approved two major projects of doubling i.e., Mudkhed – Medchal & Mahbubnagar – Dhone section and Guntur – Bibinagar section in the jurisdiction of South Central Railway. These two projects will facilitate introduction of new trains and additional freight transportation to the benefit of both the Telugu States. The projects will aid in the socio-economic development of the regions in terms of triggering economic development in the area and will facilitate smooth mobility for the goods and people.

The Salient Features of the Projects are as detailed below:

1.     Mudkhed-Dhone Doubling project (417.88 Km)

The proposed project will increase the existing line capacity of the section causing smoothening of the train operations and improve punctuality as well as wagon turn round time.

-        It will facilitate reduction of congestion and increase of rail traffic.

-        The estimated cost of this project is Rs. 4686.09 crore.

The Cabinet Committee of Economic Affairs approved the instant project of doubling of “Mudkhed-Dhone (417.88 Km)” on South Central Railway at an estimated cost of Rs.4686.09 crore proposed by Ministry of Railways.

In line with the Hon’ble Prime Minister Shri Narendra Modi Ji’s vision of a New India, the project is going to ease operations and congestion, providing the much required infrastructural development in one of the busiest sections of Indian Railways. The project will make people of this region ‘Atmanirbhar’ by creating multitasking workforce in the region which will enhance their employment/self employment opportunities. The project will also boost the’ Pradhan Mantri Kaushal Vikas Yojana” through skill development of the people.

Mudkhed-Dhone section (417.88 km) will ease the traffic congestion between Balharshah-Kazipet-Secunderabad and Kazipet-Vijayawada as Goods traffic bound to North-South can be routed via new Double Line section. It will be an alternative coal and steel route for Balharshah-Ramagundam-Secunderabad-Wadi-Guntakal and will decongest the existing busy route and enhance the traffic between southern regions and northern regions of India.

Mudkhed – Dhone section connects the northern & western part of the country with southern region. Over the years, there has been gradual increase in the number of both Freight and Passenger traffic, due to teh steadily increasing demand. The line capacity utilization of Mudkhed-Dhone section is 167 % leading to detention of both Passenger and Goods in this critical section. Thus, doubling of this section will aid in easing the saturation of this critical section.

The main industrial clusters / corridors that are being served by this section includes:  

a)  Coal:  Ramagundam, Mancherial & Mandamari

b) Economic Corridors:  Raichur-Devarkadra (EC-10), Kurnool-Pileru (EC-17), Kodangal-Mahabubnagar (EC-37), Abdullahpurpet-Chityala (EC-6), Sangareddi-Hyderabad (EC-23) & Muthangi-Manchirevula (EC-6)

c) Thermal Power Plants : MAHAGENCO at Parli, KPCC at Raichur and Yermaras in Karnataka, APGENCO at Muddanur in Andhra Pradesh

d) Food Grains: Mudkhed,Bodhan,Nizamabad,Kamareddy, Jadcherla & Mahbubnagar, Kurnool town

e) Industrial Cluster: Hyderabad, Niazamabad,Nanded, Medak, Kurnool, Gadwal, Itikiyala, Gundlapochampally, Bahadurpally

f) Warehouses & Cold storages: Nizamabad, Bodhan, Sarangapur, Bandamallaram , Mahbubnagar, Gadwal

The salient features of this Doubling project are as follows:

 

Length of line

417.88 Km

1.       

Estimated Gross Cost

4686.09 Crs

2.       

No of Junction Stations

06 Nos

3.       

No of Crossing Stations

39 Nos

4.       

No of Halt Stations

20 Nos

5.       

State covered

Maharashtra (49.15 km), Telangana (294.82 km) & Andhra Pradesh (73.91 km)

6.       

Maximum Permissible Speed

130 Kmph

Important bridges (Nos)

06

Major bridges (Nos)

34

Minor bridges (Nos)

653

Level Crossing

117

RUB(extension)

32

Traction

Electric (OHE2x25KV traction)

Districts Covered:

The Project passes through: Nanded district of Maharashtra; Nizamabad, Kamareddy, Medak, Medchal Malkajgiri, Mahabubnagar, Wanaparthy & Jogulamba Gadwal districts of Telangana; and Kurnool district  of Andhra Pradesh.

Benefits:

  •        The project eases the congestion in this critical and saturated section.
  •        It paves the way for introduction of new trains into the section.
  •       It will strengthen the connectivity between the Northern and Western part of the Country with Southern region.
  •     It will help in improving the average speed of the trains and reduce detentions in the section.
  •       It will aid in the Socio-economic development of the region and will act as major fillip to the industrial and agriculture clusters in the region served by it.

 ******* 

2.     Guntur – Bibinagar Doubling project (239Km):

  • The proposed project will increase the existing line capacity of the section causing smoothening of the train operations and improve punctuality as well as wagon turn round time.
  •  It will facilitate reduction of congestion and increase of rail traffic.
  • The project will also generate direct employment for about 75 lakh man days during construction
  •  The estimated cost of this project is Rs. 2853.23crore.

The Cabinet Committee of Economic Affairs approved the project of doubling of “Guntur - Bibinagar (239.00 Km)” on South Central Railway at an estimated cost of Rs. 2,853.23 crore proposed by Ministry of Railways. This project will generate direct employment for about 75 lakh mandays during construction.

In line with the Hon’ble Prime Minister Shri Narendra Modi Ji’s vision of a New India, the project is going to ease operations and congestion, providing the much required infrastructural development in one of the busiest sections of Indian Railways. The project will make people of this region ‘Atmanirbhar’ by creating multitasking workforce in the region which will enhance their employment/self employment opportunities. The project will also boost the’ Pradhan Mantri Kaushal Vikas Yojana” through skill development of the people.

Guntur-Bibinagar section (239 km) connects southern and eastern parts of India (Andhra Pradesh, Tamilnadu, Orissa etc) to central and western part of the India (Telangana, Karnataka, Maharashtra etc.). It is the shortest route from Secunderabad to Guntur / Vijayawada and doubling of the section improves the mobility between Secunderabad and Guntur / Vijayawada. Guntur-Bibinagar is an alternate route between Secunderabad and Vijayawada avoiding highly congested and stressed route via Kazipet, Warangal and Khammam.

The line capacity utilization of Guntur – Bibinagar section is 148.25%. Passenger and Goods trains are suffering due to detention in this section. Over the years, Freight and Passenger traffic from southern and eastern parts of India to central and western parts of the India has been increasing. Doubling of this section will lead to easing of the section and facilitate meeting the demand of ever increasing transportation needs of both our passenger and freight customers.

 

The major industrial cluster / corridors being served by the line includes:

 (a) Iron & Steel: at Chityal&Narkatpally.

(b) Cement Plants: at Vishnupuram, Nadikudi, Tummalacheruvu, Janpahad, Mellacheruvu, Muttampalli, Jaggayyapeta, Ramapuram etc.,

(c)  Thermal Power Plant : 4000 MW Thermal plant near Vishnupuram (upcoming)

(d)  Food Grains: FCI siding at Nagireddipalli, Nalgonda, Miryalagudaetc.,

(e)  Industrial cluster: Hyderabad,  Vijayawada, Guntur, Vishnupuram, Narkatpally etc.,

(f) Warehouses & Cold storages: More than 100 Ware houses around Hyderabad & more than 50 Cold storages around Guntur

Districts Covered:

The Project passes through Guntur & Palnadu Districts of Andhra Pradesh and Nalgonda & Yadadadri-Bhuvanagiri Districts of Telangana. The total area of these Districts is 23,180.38 Sq.km.  There are 1,070 Villages in these Districts which are near to the Project area.  These Districts have combined population of 80,77,172.

The important Towns, Cities near to the project area are Hyderabad (30 km from Bibinagar), Nalgonda, Nakrekal, Narkatpalli, Bhuvanagiri, Chityal, Miryalguda, Huzurnagar, Dachepalli, Piduguralla, Satennapalli, Guntur and Vijayawada which is 30 km from Guntur.

Benefits:

·    This proposed doubling will facilitate faster transportation of agricultural products, cement, coal and other local products, seamless movement of people within Telangana and Andhra Pradesh and with other parts of the country.

·      It will also reduce the journey time of the various trains running between Secunderabad and Guntur/Vijayawada stations.

·      Doubling of Guntur – Bibinagar section will increase the capacity of the section. Thus, more goods and passenger trains can be introduced in the system.

·       The project has high socio-economic relevance for the Project Focus Zone in terms of triggering economic development in the area and facilitating of smooth mobility for the goods and people.

 